Starting on the Walls and Windows

Hello everyone,

This past week, the concrete floor was poured, the windows were put in, the brick work around the building was placed and they are starting the EIFS installation today.  Also the storm drainage reservoir installation has started.  The drainage has really wrecked havoc on our parking lot as there are piles of stone to be placed over the storm pipes.  A lot of crews are working at the same time, so parking has been limited as well.  We did remove the previous trees stump as well as it will be interfering with the concrete sidewalk.

Here are the updated pics:



Old tree stump grinded down.  We will have a side walk coming through here.

Side windows.  The 5 operatories facing east each have their own window.  The 6th operatory is facing North. 

Here you can see where the cultured stone will be placed and where the sign will be at the entrance.

The North East corner of the building.  The brickwork is going up.  The rest of the building will be EIFS.  A sign will also be placed on the north side of the building. 

Next week we should have the wall studs up, the ceiling drywall will be up and duct work will be started.  EIFS will be placed and next week the cultured stone work will be done.  We are on schedule and I hope we stay on schedule to finish in December.   I will get more pics to update soon God willing. - NKS